Chief Commissioner Maheshwar Rao directed officials to expedite the completion of the Wind Tunnel Underpass project by deploying additional manpower and machinery.
During his inspection visit today to the Wind Tunnel Junction near the U.R. Rao Satellite Centre on Old Airport Road under the Bengaluru Central City Corporation limits, he instructed officials to utilise additional personnel and equipment to ensure the project is completed within the stipulated timeline.
Utility relocation works related to the underpass project, including BWSSB pipelines, sewer lines, BESCOM cables, OFC cables and other utilities, are currently in progress. He directed officials to complete the relocation work within 10 days and commence construction of the retaining wall thereafter.

To ensure uninterrupted vehicular movement, temporary roads should be constructed expeditiously on both sides of the junction through defence land, ISRO, NAL premises and private properties, wherever feasible, to facilitate traffic movement. The work should be executed in a manner that prevents traffic congestion. He also instructed officials to ensure all necessary safety measures are in place during the execution of the project.
70% of the Work Completed:
The Wind Tunnel Junction underpass project is being undertaken at a cost of ₹19 crore and involves the construction of a 300-metre-long underpass. A six-lane underpass with a width of 7.5 metres on either side is being constructed. At present, nearly 70% of the work has been completed, including utility relocation, construction of RCC retaining walls, service roads, and fabrication of the boxes that will be installed in the central portion of the underpass.
Stages of the Underpass Project:
The utility relocation work is nearing completion, and retaining wall construction will commence within the next 10 days. Subsequently, the prefabricated boxes prepared for the central section will be installed, followed by the construction of service roads in the final phase of the project.
Bengaluru Central City Corporation Commissioner Rajendra Cholan, Executive Engineers and other officials were present during the inspection.


More Stories
From Engineering to Khaki: R. Hithendra’s Three-Decade Journey in Police Service
Permanent Solutions to Bengaluru’s Civic Issues Are Government’s Aim: CM
Bengaluru West Corporation to Prepare Solid Waste Management Micro-Plans for All Wards