Bengaluru, Nov. 25:
Chief Commissioner Maheshwar Rao has directed BDA officials to complete the construction of the new Hebbal loop within 15 days and open it for vehicular movement.
Speaking during an inspection across various locations within the Bengaluru North City Corporation limits, he noted that the flyover connecting KR Puram to the city has already been completed by the BDA and opened for traffic. In continuation, the loop connecting the new flyover to the existing one is under progress, and officials have been instructed to complete it within the next 15 days.
The first girder of the new loop at Hebbal flyover has already been installed and concrete work is underway. He instructed that the remaining two girders be installed and all pending works be completed at the earliest.
Plan for a New Flyover:
BDA officials informed that discussions are underway with various departments regarding a 1.4 km flyover from Esteem Mall on Ballari Road to Manyata Tech Park, and steps will be taken to implement the project soon.
Maintain Footpaths in Good Condition:
The footpath near Hebbal Lake has been damaged in some stretches, and instructions were issued to repair and restore it. He also directed officials to immediately remove the fallen pole and clear garbage dumped along the roadside to maintain cleanliness.
Milling and Asphalting:
One section of the Hebbal flyover has already been milled and asphalted. He instructed officials to complete milling and asphalt works on the remaining portion as well.
Inspection of Ongoing Road Asphalting:
To facilitate arterial and sub-arterial road connectivity, he inspected various locations in RMV 2nd Stage and Basaveshwar Nagar where asphalting works are underway, and instructed that the works be completed quickly.

He also directed officers to examine whether a building under construction adjacent to a corporation site in RMV 2nd Stage has encroached upon corporation land, and to take action as per rules if encroachment is found.
Nagawara Junction Development:
The BWSSB is required to lay a 600/700 dia sanitary pipeline for a stretch of 1 km from Ibis Hotel to Nagawara SWD. Approval has been granted by the North Traffic Division, while approval from the East Traffic Division is pending. BWSSB officials stated that the work would begin from the northern side.

The 1000 mm culvert pipeline work by B-SMILE across the Outer Ring Road at Nagawara Junction has been completed, but the chamber construction remains pending. He directed that this work be completed soon and that water leakage in the area be fixed.
Road-widening work from Tannery Road to Nagawara Junction is in progress, and he instructed acquisition of required land through TDR to create a free-left at the junction.

Since the asphalt laid within 200 meters around the junction is frequently getting damaged, he instructed the use of M60 concrete to ensure long-lasting repairs.
During the inspection, North City Corporation Commissioner Pommala Sunil Kumar, Joint Commissioner Mohammad Naem Momin, BDA Executive Engineers, and officials from BMRCL, BWSSB, Traffic Police, and several other departments were present.


More Stories
From Engineering to Khaki: R. Hithendra’s Three-Decade Journey in Police Service
Permanent Solutions to Bengaluru’s Civic Issues Are Government’s Aim: CM
Bengaluru West Corporation to Prepare Solid Waste Management Micro-Plans for All Wards