World Bank Team Appreciates GBA’s Innovative Storm Water Drain Development and Public Walking Path at Varthur Kodi

Spread the love

Bengaluru, Sept. 04:

A World Bank Task Team visiting Bengaluru to inspect the ongoing works under the Karnataka Water Security and Resilience Project (KWSRP) funded by the World Bank visited the stormwater drain (SWD) works at Varthur Kodi Circle in Mahadevpura Constituency.

During the field visit, the World Bank team inspected the innovative approach adopted by the Greater Bengaluru Authority (GBA)/Project Implementation Unit (PIU) for developing and improving the stormwater drain while simultaneously creating a public recreational and walking facility along the drain.

The World Bank team appreciated the efforts of the GBA/PIU engineers in converting an earlier earthen drain of approximately 7–8 meters in width into a properly developed SWD corridor extending to about 30–32 meters at the selected stretch, wherever government land was secured and made available.

Integrated SWD and Public Walking Path:

A major feature appreciated by the World Bank team was the creation of an approximately 3.5-meter-wide public walking path for nearly 1 kilometer along the developed SWD.

The initiative has been implemented by securing and utilizing available Government ‘Karab’ land, removing/avoiding encroachments wherever feasible, widening the drainage corridor, and providing public access without compromising the hydraulic function of the drain.

The engineers explained that the walking path has been planned not merely as a recreational facility but also as a means of protecting government land from future encroachment and ensuring continued public use of the corridor.

Green and Environment-Friendly Development:

The GBA/PIU has incorporated landscaping and plantation measures along the corridor. Dancing/Facing Bamboo has been planted along the drain-side portion, while Tabebuia species and other suitable trees have been planted along the boundary of the corridor.

The plantation is expected to:

  • Enhance the visual appearance of the SWD corridor;
  • Provide a greener and more pleasant environment for pedestrians;
  • Help protect the government land boundary;
  • Improve the overall environmental quality of the area;
  • Create a safer and more attractive public walking space; and
  • Encourage healthy outdoor activities among local residents.

The World Bank’s Environmental and Social (E&S) specialists also expressed appreciation for the initiative, particularly for integrating environmental improvement, public access, land protection, and social benefits into the SWD development.

Provision for Sewer Infrastructure:

Another important feature demonstrated to the World Bank team was the provision made within the corridor for future/associated sewer infrastructure.

The engineers explained that the required space has been planned so that the sewer line can be laid within the corridor before/alongside the walking-path development, thereby avoiding unnecessary disturbance to the newly created public facility in the future.

The integrated planning approach was appreciated, as it provides an opportunity for coordinated development of stormwater drainage, sewer infrastructure, green spaces, and public pedestrian facilities within the available government corridor.

Appreciation by World Bank Task Team:

The World Bank Task Team Leader and members of the visiting team appreciated the innovative concept adopted by the GBA/PIU engineers.

The team observed that the initiative goes beyond conventional stormwater drain construction by combining:

“Improved drainage, government land protection, green corridor, public walking facility, and future utility provision.”

The World Bank team particularly appreciated the efforts made by the engineers in addressing encroachments, securing the drainage corridor, increasing the effective width of the SWD, and converting the previously underutilized corridor into a functional public asset with environmental and social benefits.

Positive Response from Local Public:

Members of the public who were present during the World Bank team’s interaction also expressed their happiness with the development.

Local residents appreciated the creation of the walking path, improved drainage, and plantation along the corridor. They stated that the facility would provide a safe and accessible place for walking and daily physical activity while also improving the surrounding area.

The initiative demonstrates how World Bank-supported infrastructure can deliver multiple benefits to communities when engineering, environmental, social, and public-use considerations are integrated during project implementation.

The GBA/PIU intends to explore similar opportunities, wherever technically and legally feasible, to develop SWD corridors with improved hydraulic capacity, environmental enhancement, protection of government land, and public-friendly walking/recreational facilities.