Bengaluru, June 25:
Bengaluru West City Corporation Commissioner Dr. Rajendra K.V., today inspected the progress of Capital Support for Special Infrastructure Projects (CSSIP) works on the Janapriya Apartment – Madhavanagar Water Supply and Sewerage Board (BWSSB) Pipeline Road near Magadi Road in Herohalli Sub-division of the Kengeri Division of the Corporation and gave directions to the officials.
The Commissioner reviewed the development works on the 3.5 km BWSSB Pipeline Road from Janapriya Apartment to Madhavanagar. He instructed to complete all works, including road asphalting and footpaths, systematically by coordinating with the Water Board (BWSSB) and other related government agencies.
Instruction to Raise Rajakaluve Walls:
The Commissioner directed officials to raise the walls of the Rajakaluve leading up to Herohalli Lake to prevent rainwater from overflowing and causing floods.
He instructed the engineers present at the site to issue notices and clear road encroachments.
Executive Engineer Nagaraj Singri, Assistant Executive Engineers, and concerned engineers were present on the occasion.
CMIDP, CSSIP Progress Review Meeting
The Commissioner held a review meeting on June 24 with engineering department officials and contractors regarding the progress of works related to the Chief Minister’s Infrastructure Development Programme (CMIDP) and Capital Support for Special Infrastructure Projects (CSSIP) within the corporation’s limits.
Receiving information from officials on the progress of CMIDP (ward roads) and CSSIP (arterial and sub-arterial roads) works across all divisions of the corporation, the Commissioner directed that all civil works, including footpaths and drains, must be completed within a month. He stated that desilting of drains, and the repair of curbs and footpaths, must achieve 100% completion.
The Commissioner instructed the Additional Commissioner to inspect all CMIDP civil works and submit a report.
Road pothole-filling works must be completed before asphaltization (asphalting) of the roads. Footpaths must be well-organized. Grass pavers must be installed around the base of trees. If trees are broken and stumps remain, action must be taken to clear them. The concerned Assistant Executive Engineers and Junior Engineers must ensure that desilting of drains has been done and that there are no encroachments or other undesirable elements on the footpaths. Executive Engineers must ensure that footpaths on SIP roads are properly arranged.
Contractors must allocate human resources appropriately and complete the work while maintaining quality. Ensure all road safety measures, including proper footpaths, lane markings, etc on SIP roads, commissioner instructed.

More Stories
From Engineering to Khaki: R. Hithendra’s Three-Decade Journey in Police Service
Permanent Solutions to Bengaluru’s Civic Issues Are Government’s Aim: CM
Bengaluru West Corporation to Prepare Solid Waste Management Micro-Plans for All Wards