Formulate a Plan to Prevent Waterlogging on Bannerghatta Road: Maheshwar Rao

Spread the love

Bengaluru, May 30, 2026

Chief Commissioner Maheshwar Rao instructed officials to formulate a comprehensive plan to prevent waterlogging on Bannerghatta Road.

Speaking during an inspection of flood-prone areas and other locations within the jurisdiction of Bengaluru South City Corporation, he noted that the stretch near Rainbow Children’s Hospital on Bannerghatta Road gets waterlogged whenever it rains, causing significant inconvenience to motorists. He directed officials to take necessary measures to provide a permanent solution to the waterlogging problem.

The road near Rainbow Children’s Hospital is situated at a lower level than the rajakaluve (stormwater drain). As a result, when the water level in the rajakaluve rises, water flows back through the side drains, causing flooding on the road. In this regard, officials were instructed to prepare a plan to ensure the smooth flow of water through the stormwater drain. He also directed that the rajakaluve be completely desilted.

Prevent Sewage Inflow:

During the inspection, it was observed that sewage water was flowing into the stormwater drain near Hulimavu Metro Station on Bannerghatta Road. Officials of the BWSSB were directed to identify the source and take measures to prevent sewage from entering the stormwater drain.

It was also observed that utilities crossing the stormwater drain were obstructing the flow of water. Officials were instructed to install slabs and relocate the utilities above them. Further, they were directed to desilt the rainwater drain and ensure smooth water flow.

Complete BWSSB Works Within Two Days:

As part of the first phase, the BWSSB has undertaken the laying of a 900 mm dia pipeline and the connection of household sub-pipelines to the main sewer line along a 1.5 km stretch from Vega City Mall to Arekere Signal on Bannerghatta Road. Officials were instructed to complete this work within two days. Thereafter, the Corporation will undertake asphalting works and complete them within the stipulated timeframe.

After the successful completion of the first phase, the second phase of BWSSB works covering a 1 km stretch from Arekere Signal to Hulimavu Metro Station will be commenced.

Inspection of Silk Board Junction:

To address the recurring waterlogging issue at Silk Board Junction, works are underway to increase the capacity of the rajakaluve passing beneath the road from 1.5 metres to 3.5 metres. Steel gratings are also being installed above the drain. The first phase of the work is almost complete, and the road will soon be opened for vehicular movement. The remaining two sections of the culvert work will be taken up in the second phase and completed by the end of June.

Conduct Survey and Submit Report for New Drain:

Officials were instructed to conduct a survey and submit a report for the construction of a new drain near Silk Board Junction to prevent waterlogging in HSR Layout.

Take Steps for Construction of Free Left Turn:

At Silk Board Junction, the Metro Department has acquired a corner property to facilitate traffic movement from Bommanahalli towards BTM Layout. However, the Balaji Complex located on the site has not yet been cleared. Speaking to Metro officials over the phone, the Chief Commissioner directed them to remove the complex and take necessary steps for the construction of a free left turn.

Complete Junction Development Works Expeditiously:

Development works beneath the Silk Board Junction flyover are in progress. Officials were instructed to expedite the completion of beautification works, including the installation of street lighting.

Take Measures for Madiwala Lake Development:

Development works worth ₹15 crore have been undertaken at Madiwala Lake, including strengthening of the lake bund, construction of a silt trap at the inlet, a culvert at the outlet, development of a walkway, installation of gates and signboards, and construction of a security personnel room. Officials were instructed to expedite the completion of the bridge being constructed at the site.

Inspection of Ejipura Flyover Works:

During an inspection of the portal frame works near St. John’s, directions were issued to complete the Domlur-side ramp within a week and the Madiwala-side ramp within 60 days. The contractor was also instructed to deploy two additional work gangs and accelerate the bearing installation and expansion joint works.

MLA Satish Reddy of Bommanahalli Assembly Constituency, Special Commissioner Sushama Godbole, City Corporation Commissioner Ramesh K.N., Additional Commissioner Naveen Kumar Raju, Chief Engineers Ravi and Rajesh, and officials from the BWSSB and various other departments were present during the inspection.